-
Zion National Park South Gate Renovation
Zion National Park "South Gate Entrance Remove and Construct Fee Buildings". The Scope of Work includes Removing existing fee stations and providing temporary modular stations during the construction period and constructing four new fee stations with an overhead canopy. The sitework consists of new utilities, new concrete and asphalt lanes, landscaping and expanded incoming and outgoing traffic lanes.
-
BLM Grand Junction, Colorado Air Center Pavement Repair/Replace Phase 1
Replacement and repair of the Retardant Apron Pavement at the Grand Junction Air Center for the BLM Fire Program. The work included the Full depth removal of areas of existing asphalt and concrete pavements, Over-excavation and haul off site of unsuitable subgrade soils, Import and placement of suitable subgrade soils, Reconstruction of concrete and asphalt pavement sections, Associated drainage, sediment controls and other incidental work items Mill and replace upper 3.5-inches of areas of existing asphalt pavement. Bill has managed many projects for the BLM throughout Colorado, putting together to cost estimates and writing the proposals along with managing the performance of the contracts.
-
US Air Force Academy Asbestos Abatement Colorado Springs, Colorado
Direct award contract with the United States Air Force Academy in Colorado Springs, Colorado. The purpose of this project was to provide services to perform asbestos abatement in the Mitchell Hall ceiling plenum that meets the intent of CCR 8 and provide oversight of the Spill Response Cleanup as the Building Owner Representative.
"Given what I know today about the contractor's ability to perform in accordance with this contract or order's most significant requirements, I would recommend them for similar requirements in the future."
- Aaron Vollbracht Contracting Officer -
-
DOI Fish and Wildlife Services Design/Build Fabric Structure Hotchkiss, Colorado
Design/Build Fabric Structure contract for the Department of Interior Fish and Wildlife Services at the Fish Hatchery in Hotchkiss, Colorado. The first day on-site we began excavation for the continuous footings and foundation walls, as specified and designed; however, we ran into two main drainage 3' pipes running North/South on the inside of both the East and West foundation walls and through the foundation on the North and South walls. We issued a stop work request and demobilized that same day. We immediately went to work redesigning the footings and foundations on the North and South walls to include concrete columns instead of continuous concrete. We were able to complete this project on time and without requesting additions funds.
-
Tooele Army Depot Railroad Upgrade Tooele, Utah
"This letter of reference is for Bill Mounga an employee of M Construction in Orem, Utah. Mr. Mounga was the project manager for a railroad upgrade project at the Tooele Army Depot in Tooele, Utah. Mr. Mounga was tasked with coordinating work between the railroad subcontractor for their company and a railroad contractor for the Army. Each firm had specific work assigned and M Construction was faced with many time issues as the Army contractor appeared to be working on a time and materials type contract. M Construction had to perform their part of the work after the Army Contractor had completed their part. As "time" was not a concern for the Army Contractor. Mr. Mounga did a very good job in coordination as their subcontractor was aggressive and worked to complete on schedule."
- Marjorie C. Rosenquist Contracting Officer -